|
| |
Town of Normal, IL
In the spring of 2003, the Town of Normal began
construction on a water main improvement project to improve the quality of water
supplied to the residents of Normal, IL. Originally, 2 HDD installation of
8" Ductile Iron Pipe were planned. one crossing under a bridge for
approximately 300' and another crossing under a pedestrian pathway and through a
very narrow right of way between residential properties for about 800'.
Both locations would have been very difficult to complete via conventional
trenching. Upon completion of the two crossings, the General Contractor,
Colclasure, Inc. elected to have us attempt HDD installations on some other
sections of the project, most notably the areas within the historic district
under brick paved streets. The town required as a condition of the
contract that if the brick pavers were to be removed, they would need to be
replaced in kind, making restoration a very expensive task. By installing
the ductile iron pipe via HDD and only open cutting at locations for valves,
fittings and service connections, the restoration cost for the general
contractor was greatly reduced. Another derived benefit of the HDD
installation was the greatly reduced impact on the surrounding community from
construction activities that ordinarily would have required many streets to be
closed down and rerouted. Over 4000' of restrained joint ductile iron pipe
was dilled and pulled, and none of the drilled sections failed the hydrostatic
pressure tests. For more information on this project, see the Journal AWWA
article Ductile
Iron Pipe Goes A Different Direction, Is That Normal?
|
 |
Village of Riverwoods, IL
In the fall of 2001, our crews completed multiple
installation of 12" restrained joint ductile iron pipe including, what to
the best of our knowledge is a standing record today, 2,160' in one single
pull. The project was initially conceived to bring water to the residents
of Riverwoods, IL who were currently on a well system. The majority of the
4000' of pipe was to be installed along the main 2-lane thoroughfare in town.
The right of way was heavily wooded on either side of the road and traffic
disruption was a major concern. Additionally the ground conditions were
very sandy with high ground water levels. A traditional open trench
installation of the pipe would have been very time consuming, expensive and
disruptive to the community. HDD was selected as the method of
construction and the entire project was completed in just 3 separate installations.
Upon completion of the base contract, the village requested a change order for
the installation of another 2500' of 12" ductile iron via HDD in a separate
section of town.
|
|
|